JAC Construction Update Vlog: Episode 5
Isaac is joined by Tyler Shupe with Wadman to discuss the new Security Checkpoint progress.
Read MoreIsaac is joined by Tyler Shupe with Wadman to discuss the new Security Checkpoint progress.
Read MoreTerminal Projects Terminal Projects are on schedule. Basement excavation is underway. The new Security Checkpoint and Hold Room area roof is complete. Concrete flooring and wall framing is underway. Runway Project We are at Day 22 of our 78 Day Runway Project and on schedule. Milling is approximately 80% complete for removal of the […]
Read MoreConstruction is happening 24/7 (day and night, rain or shine). Materials from the restaurant and security checkpoint projects are being incorporated into the runway project negating the need to truck offsite. The hold room and security checkpoint area roof is nearly complete; all the steel has been installed and they will be pouring the first […]